Chilalo Graphite Reserve Confirms Robust Potential
Friday, 17 August 2018 05:40 PM
IMX Resources Limited (ASX: IXR) (‘IMX’ or the ‘Company’) is pleased to announce the declaration of the maiden Ore Reserve for its Chilalo Graphite Project located in south-east Tanzania. The Ore Reserve estimate was prepared primarily to assist in addressing concerns raised by the Australian Securities and Investments Commission (‘ASIC’) in relation to a prospectus lodged by Graphex Mining Limited (‘Graphex’) on 4 April 2016 (the ‘Original Prospectus’) (see ASX announcements 27 April 2016 and 3 May 2016).
The Ore Reserve estimate was prepared by CSA Global Pty Ltd (‘CSA’), an experienced and respected mining engineering consultancy with appropriate graphite experience.
The Ore Reserve estimate is based only on the Indicated Resources at the Chilalo Project of 5.1 Mt grading 11.9% TGC for 613,800 tonnes of contained graphite included in the high-grade Mineral Resource estimate that also includes Inferred Resources of 4.1 Mt grading 9.1% TGC for 370,300 tonnes of contained graphite (see ASX announcement 13 October 2015).
The Ore Reserve estimate, together with a replacement prospectus lodged with ASIC by Graphex on 10 May 2016 (the ‘Replacement Prospectus’), is expected to address concerns raised by ASIC regarding forward looking statements included in the Original Prospectus. The Company expects to provide an update later today on ASIC’s consideration of the Replacement Prospectus.
The Ore Reserve estimate for the Chilalo project as at May 2016 is outlined in Table 1 below:
Table 1. Chilalo Project Ore Reserve
|
Reserve Category |
Tonnes (Mt) |
Grade (TGC%) |
Contained Graphite (Kt) |
|
Proved |
- |
- |
- |
|
Probable |
4.7 |
11.0% |
516 |
|
Ore Reserves total |
4.7 |
11.0% |
516 |
Managing Director Phil Hoskins commented, “The declaration of a maiden Ore Reserve continues to support our view that Chilalo is an outstanding project. We are particularly pleased that almost 85% of the Indicated Resources were converted to Probable Reserves, which demonstrates the predictability of the ore body and the robust nature of the project. We expect that this will support our ongoing discussions with China Gold and CN Docking during this period of exclusive due diligence to assess the potential for the joint development of the Chilalo Project. It will also allow us to proceed with the Graphex spin-off which has built strong momentum in anticipation of concluding a transaction with China Gold in the coming months and resulting in investor interest well in excess of the planned maximum raising.”
CSA Global Pty Ltd recently prepared a second project plan that contained only Indicated Resources. This plan was established using an adjusted mine design and schedule while maintaining the same key technical and economic parameters contained in the PFS, including the same processing plant, production rates, capital costs and unit operating costs.
A project financial model, generated for the smaller Ore Reserve plan and using the same financial parameters as the PFS, demonstrated that the outcome for the Ore Reserve project case was economically viable with a positive NPV (although less than the PFS), the same payback period as the PFS (within two years) and retaining a pre-tax Internal Rate of Return (IRR) greater than 50% (see Section 4 of Appendix 1).
Information required under ASX Listing Rule 5.9.1
In accordance with ASX Listing Rule 5.9.1, the Company provides the following information:
- A PFS was completed by IMX for the Chilalo Project, (see ASX announcement 23 November 2015) for full details of assumptions employed.
- The study proposed an operation processing 630 ktpa of ore to produce a nominal 69ktpa of graphite concentrate, comprising 51ktpa of coarse graphite flake concentrate and a further 18ktpa of fines for a mine life of approximately ten years. The PFS found that the project is physically and economically viable, with a strong Internal Rate of Return (IRR) and a pre-tax payback of less than two years.
- The PFS is based on production from Indicated and Inferred Resources and for this reason the full amount mined in the PFS is not appropriate to be included in an Ore Reserve estimate.
- A Probable Ore Reserve estimate was developed considering only the Indicated portion of the mineral resource that underpins the Chilalo Project, applying all of the Modifying Factors, parameters and considerations of the PFS to produce a mine life of approximately eight years at the same production rates and with the same product specifications as the PFS. As only Indicated material was used to estimate the Ore Reserve, there is a smaller volume of production.
- Production from the Ore Reserve’s eight years of the project is very similar to the first eight years of the ten-year PFS. Many key financial measures are very similar, with the post-tax payback period for both cases less than two years and the post-tax IRR for the Ore Reserve case is greater than 50%.
- Classification
- Classification of the Mineral Resource estimates was carried out taking into account the level of geological understanding of the deposit, quality of samples, density data and drill hole spacing.
- The Mineral Resource estimate has been classified in accordance with the JORC Code, 2012 Edition using a qualitative approach. All factors that have been considered have been adequately communicated in Section 1 and Section 3 of this Table.
- The Mineral Resource estimate appropriately reflects the view of the Competent Person.
- No Measured Resources have been estimated for the Chilalo project.
- The Ore Reserve estimate considers only Indicated Resources and does not include any quantity of Inferred or unclassified material. Thus, the Ore Reserve estimate comprises only Probable Ore Reserves.
- The mine plan used in the Ore Reserve estimate includes approximately 7% of inferred material that is mined during the process of accessing the Indicated ore. This Inferred Resource is not considered material to the value of the project and is not included in the estimation if the Probable Reserve.
- The result appropriately reflects the Competent Person’s view of the deposit.
- Mining
- The mining method for the Chilalo Graphite Project is conventional open pit mining, using excavators and trucks for load and haul operations. Drill and blast operations will be conducted as required.
- The Chilalo deposit is a generally planar, steeply dipping deposit with clearly defined contacts. Mining dilution and recovery is based on typical values for this style of deposit and mining method. Mining recovery of 95% of tonnes has been applied, with a dilution component of 5% (at zero grade)
- Processing
- A representative testwork program demonstrated that the ore from the Chilalo Graphite Project is amenable to the production of high-grade graphite concentrates, at coarse flake sizes, using relatively simple flotation processes. These processes are an established process of recovery for graphite, used successfully in the industry.
- Consideration for deleterious elements was completed on a general level suitable for a Probable Reserve. Further consideration on a more specific level will be completed as product specifications are refined.
- Cut-off Grade
- The revenue generated from a graphite operation is primarily driven by the flake size distribution of the product. The flake proportion over a series of size categories determines the basket price of the product. The carbon grade (TGC) is not directly related to flake size.
- This Ore Reserve estimate is based on a cut-off grade of 8% TGC. This cut-off grade is based on a distinct population step in the Mineral Resource estimate at this grade and a link identified in the mineralogy of the deposit where flake size distribution has a step improvement above 8% TGC.
- Project economics from the total project have been considered at the end of the full project iteration to confirm that the cut-off criteria support economic operations for the Chilalo Graphite Project.
- Estimation Methodology
- The Chilalo Ore Reserve estimate is based on a detailed block model of the Mineral Resource and a detailed mine design. The Ore Reserve is based on a spatially supported and explicit mining schedule.
- Material Modifying Factors
- Material modifying factors including land access, infrastructure requirements and logistics have been addressed in the Chilalo Graphite Project PFS (see ASX announcement 23 November 2015) to an adequate level of confidence for a Probable Ore Reserve.
- The Chilalo Graphite Project has been issued with an Environmental Certificate by the National Environment Management Council of Tanzania. This certificate is a pre-requisite for the granting of a Mining Licence.
PHIL HOSKINS
Managing Director
|
For further information, please contact: Phil Hoskins – Managing Director Tel: +61 8 9388 7877 Media: Michael Weir/Richard Glass – Citadel-MAGNUS Telephone: +61 8 6160 4903 |
Stuart McKenzie – Commercial Manager and Company Secretary Tel: +61 8 9388 7877
|
Competent Person’s Statement
The information in this report that relates to Chilalo Ore Reserves is based on information compiled by Mr Karl van Olden, a Competent Person, who is a Fellow of The Australasian Institute of Mining and Metallurgy. Karl van Olden is employed by CSA Global Pty Ltd, an independent consulting company. Mr van Olden has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr van Olden consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
Previously reported Information
- This news release includes information that relates to the Mineral Resource estimate announced on 13 October 2015. Since announcing the Mineral Resource estimate on 13 October 2015, IMX confirms that it is not aware of any new information or data that materially affects the information included in that announcement and that all material assumptions and technical parameters underpinning the Mineral Resource estimate in that announcement continue to apply and have not materially changed.
- This news release includes information that relates to the results of the PFS announced on 23 November 2015. Since announcing the results of the PFS announced on 23 November 2015, IMX confirms that that it is not aware of any new information or data that materially affects the information included in that announcement and that all material assumptions and technical parameters underpinning the results of the PFS continue to apply and have not materially changed).