Asiamet Fiscal 2016 Results

Friday, 17 August 2018 05:40 PM

Asiamet Resources Limited ("ARS" or the “Company”) Financial Statements and Management Discussion & Analysis (“MD&A”) for 2016 are available for viewing on www.sedar.com or www.asiametresources.com and have been provided to shareholders who have requested a hard or electronic copy.

 

The highlights of the Company’s activities in the 2016 year and up to the date of the MD&A report are summarized below.

 

Operations

 

  • Asiamet announced the results of the independently prepared Preliminary Economic Assessment (“PEA”) study on April 5, 2016.  The study was filed on the Company’s profile on www.sedar.com on May 19, 2016.  The PEA is the first study undertaken to evaluate the potential economics of developing an open pit mine and heap leach solvent extraction electro-winning facility ("SX-EW") to directly produce copper cathode based on the near surface copper deposit reported in the 2015 BKM Resource estimate (ARS NR October 21, 2015).  Results of the PEA study demonstrate excellent potential for developing a robust, low strip ratio, low capital intensity copper project with low operating costs, strong cash flow generation capacity and significant upside potential through further Resource growth.

 

  • At the BKM site a comprehensive Resource infill and extension drilling program began at the end of May 2016 and continues at the time of this report.  The goal of the 50-meter spaced grid drill program is to upgrade the Inferred Mineral Resource i.e. 49.7million tonnes grading 0.6% Cu containing 657 million pounds of copper at (0.2% Cu reporting cut), to the Measured and Indicated Mineral Resource categories.  Several large diameter (PQ size) core holes were completed to collect fresh bulk samples for detailed metallurgical testwork.  Approximately 120 holes/12,500 meters of Resource drilling and 15 holes/2000 meters of metallurgy drilling will be completed.

 

  • As announced on April 12, 2017, 112 holes for 11,500 meters of diamond core drilling had been completed and 3 holes were in progress.  The infill / expansion drill campaign has been extended to approximately 12,500 meters, with the final 1,000 meters to be completed by the end of April 2017.  Additional holes were drilled on section lines BKM31900 and BKM32650, and several holes were extended to deeper levels to test the spatial continuity within selected mineralized domains.  Results from the program have met or exceeded our expectations in respect of both grade and continuity, particularly within the higher grade BKM044 and BKM058 zones.  While the program has been very much focused on Resource definition, some extension areas requiring further evaluation have also been identified for future follow up.  The geometry of the mineralization and both the lateral and vertical continuity of this mineralization at BKM are expected to contribute to a positive Resource update to be issued shortly after results of these last few remaining holes are received and incorporated into the Resource model.

 

  • The Company contracted a number of the key consultants and service providers required to oversee the long lead time items of the feasibility study and work programs in each of the key disciplines are underway.

 

  • Australian Mine Design and Development (“AMDAD”) completed a Project Definition Study (“PDS”) to address the scope of work, which builds upon planning from the PEA on the BKM Project.  The PDS updates the cost and revenue assumptions from the PEA and provides a sufficiently detailed potential open pit design and schedule to demonstrate the practicality of the mine plan including an updated assessment of the site layout.  This updated design and schedule potentially offers major operational and cost benefits compared to the PEA design.

 

  • On February 23, 2017, the Company announced the results of a comprehensive review of all historical exploration data collected within a 3 kilometer radius of the BKM deposit.  The review assessed the base and precious metal potential at each of the Beruang Kanan West (“BKW”), Beruang Kanan South (“BKS”) and BKZ Polymetallic Prospects.  Significant copper, zinc and associated base and precious metal mineralization warranting near term drill testing is present on each of the key prospect areas.

 

  • On February 16, 2017, the Company formally established with the Government of the Republic of Indonesia that the KSK CoW has now entered the Feasibility Study Period which runs for not less than two years, is extendable, and provides time to complete studies and identify the area for mining.  The KSK Cow has a total of 30+ years remaining for exploration, development and operations.

 

Financials

 

  • The Company began the current fiscal year with $778,634 in cash with $2,847,342 used in operating activities; $23,987 used in investing activities; $3,840,225 contributed by financing activities; to end the year with $1,747,530 cash.  The Company expects to receive $700,000 proceeds from the sale of its Jelai project by May 15, 2017.

 

  • The Company incurred a loss for the year ended December 31, 2016, of $3,794,364 (2015 – $7,421,022).  This loss is wholly attributable to the exploration and development programs completed on the Company’s projects and the technical, financial, legal, commercial, external (government and community) and investor relations activities required to support these programs, and the Company’s business objectives.

 

Attached are the audited Consolidated Statements of Financial Position, Consolidated Statements of Comprehensive Loss, Consolidated Statements of Cash Flows, Consolidated Statements of Changes in Equity (the "Financial Statements") of the Company for the fiscal year ended December 31, 2016.

 

Operations Plan – 2017

 

The 2017 program at BKM will focus on long lead time items for the bankable feasibility studies and exploration and resource drilling to increase potential mine life including:

 

  • Detailed stage 3 metallurgical studies to optimize copper recoveries i.e. short and long column  leach test work, Resource variability studies

 

  • Drilling to upgrade Resource confidence to Measured and Indicated Status

 

  • PFS level project option analysis, optimisation and value engineering studies

 

  • Exploration and Resource delineation drilling at BKM, BKW and BKS to expand Resource base and demonstrate a +10 year life for BKM. 

 

  • Environmental impact assessment (AMDAL)

 

Various corporate initiatives focused on partnering and funding for the ongoing development of the Company and its projects are being progressed.  Asiamet has received several approaches from parties interested in partnering on the development of BKM either through off-take agreements or equity partnership.  This avenue of financing the bankable feasibility study and ultimate development of the project will continue to be investigated.

 

Subject to receipt of a forestry permit and the availability of funding, Asiamet also intends drilling some additional holes into the high grade base metal vein system at Baroi prospect to assess the potential of this target for a stand-alone deposit.

 

Beutong

 

PT EMM is continuing to progress approval of an IUP Production license for the Beutong Project.  Upon receipt of the IUP Production the Company intends to re-activate field programs aimed at extending near surface Resources and progressing development of the project.

 

Qualified Person

 

All technical data, as disclosed in this Pres Release has been reviewed and verified by the Company's Qualified Person for the Company’s mineral projects, Stephen Hughes P. Geo, Vice President Exploration of the Company, a Qualified Person under NI 43-101 and for the purposes of the AIM Rules.

 

ON BEHALF OF THE BOARD OF DIRECTORS

 

Peter Bird, Managing Director & CEO

 

For further information, please contact:

-Ends-

 

Peter Bird, Managing Director & CEO

Telephone: +61 3 8644 1300
Email: [email protected]

 

Tony Manini


Chairman, Asiamet Resources Limited
Telephone: +61 3 8644 1300
Email: [email protected]

 

FlowComms Limited

 

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: [email protected]
 

Asiamet Resources Nominated Adviser


RFC Ambrian Limited

Andrew Thomson / Oliver Morse

Telephone: +61 8 9480 2500

Email: [email protected] / [email protected]

 

VSA Capital Limited


Andrew Raca / Justin McKeegan

Telephone: +44 20 3005 5004 / +44 20 3005 5009

Email: [email protected]

 

Optiva Securities Limited


Christian Dennis

Telephone: +44 20 3137 1903

Email: [email protected]

 

This news release contains forward-looking statements that are based on the Company’s current expectations and estimates. Forward-looking statements are frequently characterised by words such as “plan”, “expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”, “suggest”, “indicate” and other similar words or statements that certain events or conditions “may” or “will” occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements.   Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices.  There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended.  Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

 

ASIAMET RESOURCES LIMITED

CONSOLIDATED STATEMENTS OF FINANCIAL POSITION

(expressed in United States dollars, unless otherwise noted)

 

 

 

   

December 31,
2016

December 31,
2015

 

 

 

 

ASSETS

   

Current assets

   
 

Cash

$      1,747,530

$        778,634

 

Receivables and other assets

253,552

99,911

 

Subscriptions receivable

801,840

-

   

2,802,922

878,545

       

Non-current assets

   
 

Equipment

37,243

91,799

 

Security deposit

94,575

92,374

TOTAL ASSETS

$      2,934,740

$      1,062,718

       
       

LIABILITIES AND SHAREHOLDERS' EQUITY

   

Current liabilities

   
 

Trade and other payables

$      1,016,175

$        349,243

 

Related party loans

233,290

-

       

Non-current liabilities

   
 

Provision for employee service entitlements

101,875

42,377

   

1,351,340

391,620

       

Shareholders' equity

   
 

Share capital

7,060,176

5,706,741

 

Equity reserves

33,323,413

29,967,939

 

Other comprehensive loss

(2,243)

-

 

Deficit

(38,790,918)

(34,996,554)

   

1,590,428

678,126

 

Non-controlling interest

(7,028)

(7,028)

   

1,583,400

671,098

TOTAL LIABILITIES AND EQUITY

$      2,934,740

$      1,062,718

 

ASIAMET RESOURCES LIMITED

CONSOLIDATED STATEMENTS OF LOSS AND COMPREHENSIVE LOSS

(expressed in United States dollars, unless otherwise noted)

 

 

 

For the year ended

   

December 31,
2016

December 31,
2015

 

 

 

 

Expenses

   
 

Accounting and audit

$          98,888

$          62,166

 

Consultants and shared office costs

510,230

860,707

 

Exploration and evaluation expenditures

2,689,467

6,093,147

 

Investor relations

106,164

10,167

 

Legal

6,738

19,166

 

Office and administrative services

26,270

27,120

 

Share-based compensation

300,134

208,300

 

Transfer agent and regulatory fees

108,685

112,052

 

Travel and accommodation

42,677

78,020

   

3,889,253

7,470,845

       

Other items

   
 

Non-refundable deposit received

100,000

-

 

Taxation (expense) recovery

(6,528)

56,393

 

Foreign exchange loss

(872)

(6,760)

 

Gain on sale of equipment

-

40

 

Interest income

2,289

150

   

94,889

49,823

Net loss

(3,794,364)

(7,421,022)

Items that may be reclassified subsequently to profit or loss:

 
 

Provision for employee service entitlements

(2,243)

-

Loss and comprehensive loss for the year

$     (3,796,607)

$     (7,421,022)

       

Loss attributable to:

   
 

Equity holders of the parent

$     (3,794,364)

$     (7,421,022)

       

Basic and diluted loss per common share

$             (0.01)

$             (0.02)

Weighted average number of shares outstanding

609,750,484

461,838,631

 

ASIAMET RESOURCES LIMITED

CONSOLIDATED STATEMENTS OF CASH FLOWS

(expressed in United States dollars, unless otherwise noted)

 

 

 

 

For the year ended

     

December 31,
2016

December 31,
2015

 

 

 

 

 

Cash provided from (used for):

     
         

Operating activities

     

Loss for the year

 

$     (3,794,364)

$     (7,421,022)

Adjustment for non-cash items:

     
 

Depreciation

 

78,543

10,548

 

Exploration and evaluation expenditures acquired

 

-

3,693,127

 

Gain on sale of equipment

 

-

(40)

 

Share-based compensation

 

300,134

208,300

 

Unrealized foreign exchange loss (gain)

 

(4,444)

16,315

Changes in non-cash working capital:

     
 

Receivables and other assets

 

(153,641)

(82,087)

 

Trade and other payables

 

666,932

34,682

 

Provision for employee service entitlements

 

59,498

19,911

     

(2,847,342)

(3,520,266)

Investing activities

     
 

Beutong acquisition transaction costs

 

-

(41,467)

 

Purchase of equipment

 

(23,987)

(1,465)

     

(23,987)

(42,932)

Financing activities

     
 

Related party loans

 

233,290

-

 

Share issues

 

3,831,110

4,518,876

 

Share issue costs

 

(224,175)

(223,548)

     

3,840,225

4,295,328

         

Increase in cash

 

968,896

732,130

         

Cash, beginning of the year

 

778,634

30,382

Cash acquired on acquisition of subsidiary

 

-

16,122

       

-

Cash, end of the year

 

$      1,747,530

$        778,634

         
         

Supplementary information:

     
         
 

Interest paid

 

$            1,342

$            3,121

 

Income taxes paid

 

-

-

         

Non-cash investing and financing activities

     
         
 

Fair value of shares issued exploration and evaluation expenditures
     a subsidiary

 

$                 -

$      3,304,490

 

Fair value of warrants issued for the acquisition of a subsidiary

 

-

414,253

 

Fair value of warrants issued to brokers included in share issue costs

 

165,815

123,730

 

Subscription receivable

 

801,840

-

 

ASIAMET RESOURCES LIMITED

CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY

(expressed in United States dollars, unless otherwise noted)

 

 

 

 

Attributable to equity holders of the parent

 

Number of shares

 Share capital

Equity reserves

Other Comprehensive Loss

Deficit

Total

 

 

 

     

 

 

574,597,071

$     5,706,741

$    29,967,939

$                      -

$        (34,996,554)

$          678,126

Share issues

135,343,618

1,353,435

3,279,515

 

-

4,632,950

Warrant issues - brokers

-

-

165,815

   

165,815

Share issue costs

-

-

(389,990)

 

-

(389,990)

Share based compensation

-

-

300,134

 

-

300,134

Loss and comprehensive loss for the year

-

-

-

(2,243)

(3,794,364)

(3,796,607)

 

709,940,689

$     7,060,176

$    33,323,413

$           (2,243)

$      (38,790,918)

$      1,590,428